These NEC solar PV and low-voltage practice questions cover Articles 690, 700, 701 and 725. Solar and low-voltage are the fastest growing part of the exam, and they are the part most older study material covers thinly. Article 690 has its own rules for conductor sizing and rapid shutdown that do not look like anything in Chapter 3. Article 725 puts low-voltage circuits into classes that decide what you can run them alongside.

Written by Kevin, a licensed Michigan master electrician — 26 years in the trade and 17 of them as an electrical inspector. Every answer below names the NEC section it comes from, so you learn where to look it up rather than memorising it.
Exam tipPhotovoltaic conductor sizing carries two multipliers, 125% for continuous duty and 125% again for irradiance. Applying only one of them is the standard error and it lands on a wrong answer that has been placed there for you.

Tap an answer to see whether you got it right, the code section it comes from, and the reasoning worked out in full. Nothing to sign up for.

Question 1Solar, Emergency & Low-Voltage

What size branch circuit is required for commercial sign?

Question 2Solar, Emergency & Low-Voltage

If the sign disconnect is not within sight, it must be _______?

Question 3Solar, Emergency & Low-Voltage

What is the maximum percentage applied to the PV maximum current when calculating the overcurrent device per 690.8(A)?

Question 4Solar, Emergency & Low-Voltage

What kind of raceway can photovoltaic (PV) circuits be run in inside a building?

Question 5Arc Flash

In other than a dwelling unit, a permanent arc flash label is required on service equipment and feeder supplied equipment rated at least how many amperes?

Question 6Arc Flash

Besides the warning itself, what must the permanent arc flash label required by 110.16(B) include?

Question 7Arc Flash

Does the arc-flash hazard warning marking of 110.16 apply inside dwelling units?

Question 8Arc Flash

Under 110.16(A), what makes arc-flash warning marking required on switchgear, enclosed panelboards and motor control centers?

Question 9Arc Flash

The NEC requires arc-flash labeling but not the arc-flash calculation. Which standard does it point to for the industry practice behind the label?

Question 10Arc Flash

The arc-flash marking required by 110.16(A) must be located so that it is what?

These are 10 of 803 questions

The full course carries 654 code and calculation questions plus 149 photo questions taken on real job sites — my own photographs from 17 years of electrical inspections. Every one of them is worked out like the ones above.

See the full course — $200 for 6 months
Work at it and still fail twice inside your six months, and you get the $200 back.

More free practice questions by topic